Eloy WWTP Expansion



Project Owner:
City of Eloy
Date:
July 1999
Location:
Eloy



Project Description

This WWTP project upgraded the existing facility by replacing the settling ponds with a Parkson Biolac system Called a Type-R Wave OX. The settling ponds were reconfigured to accommodate Parkson’s system with the addition of concrete dividing walls and pond liners. In addition to the new treatment system, a new lift station headworks facility was added that included elevated bar screens, a screw conveyor, and a new 24” main transmission line from the headworks to the Biolac system.