City of Scottsdale Zone 12 Reservoir & 13 BPS



Project Owner:
City of Scottsdale
Date:
January 2006
Location:
Scottsdale, AZ


City of Scottdale Zone 12 Reservoir City of Scottsdale Zone 12 Reservoir


Project Description

Currier Construction built a Type 1, partially buried DYK 2.5 MG reservoir and booster pump station with valve vault structures. The project was surrounded by private and state land with little area for marshalling. The project required careful planning and “just in time” delivery to accommodate the schedule and constraints. The project included a dual zone booster pump station, vertical turbine pumps, with dual hydro tank and surge control system, chlorination system, electrical/instrumentation and control work, associated yard piping and connections to the existing distribution system, site walls and landscaping.